Pease Development Authority, Airport Management Department
to: Distribution list
from: andrew pomeroy, senior airport operations agent
subject: General Aviation (GA) Apron reconstruction project Phase 4 and 4a
date:
Beginning
Starting on September 5, 2006 Phase 4a of the
GA Apron Reconstruction Project will begin.
This area consists of the concrete apron surrounding T-Hangar Units 200,
201 (T-Hangars 1-10 and 41-18) and the East side of T-Hangar Unit 203 (Hangars 12,14,16,18,
and 20). The aircraft in these hangars can be relocated to a temporary hangar
facility. This phase of construction will be closed for a period of
approximately 30 days.
Note
to T-hangar tenants affected in Phase 4a:
The Pease Airport Management will be accessing the T-hangars to inventory
the aircraft inside each. This is to
facilitate a parking plan for the temporary hangaring of T-hangar
Aircraft. Temporary hangar facilities
are for Aircraft Only. In addition,
certain phases of construction will require the hangar doors to be opened.
The
work area will be marked with orange and white plastic barricades equipped with
flashing red lights.
The
FBO’s, and Corporate Hangars will be accessible via Taxiways N, P, and Q. OPEN T-Hangars, and Pan Am Services, will be
accessible via a temporary taxi-lane through the middle of the shelter hangars
at Twy P. The taxi-lane will be marked with a yellow centerline and green
centerline reflectors. This taxi-lane will be limited to aircraft with a
wingspan of 79 feet or less.
Please
reference the attached map.
The
closure date is subject to weather and construction delays. Check airfield
NOTAMs regularly.
Please
feel free to contact me or