Pease
Airport Users’ Group Meeting
Minutes
March 15, 2006
6:30 PM
Pease Development
Authority
Board Room
I. Introduction: Andrew Pomeroy
welcomed everyone and advised that Users’ Group Meetings will now be held twice
annually. Everyone in attendance
introduced themselves.
II. Airfield
Activities:
A.
Airfield Construction: There are four major projects this construction season.
1. Taxiway A OFA
Project: On March 27 the final
phase of the TWY A project begins. Pike
will be tearing out concrete on the East side of TWYA. TWY A will be closed from TWY F to North of
TWY C. Part of TWY C will remain open because air traffic will have to
back-taxi on the runway and Charlie will be a “hold spot”. Lights and five new signs will be installed
North of TWY C, a week or two into the TWYA project and this area will be open
only to the NHANG. This part of the project is estimated to last approximately
two months.
2. GA Apron Project: Beginning on March 21, there will be saw
cutting and removal of concrete in front of half of both FBO hangars. This
first phase is scheduled for sixty days. The tie down tenants will be relocated
to west of the shelters and FBO parking will be there as well. Phase 3 will entail the other half of the
concrete in front of Port City Air.
During this phase the Tie Downs will be in place except for the taxiway
to get to the T Hangars. The Tie Downs
will be in an interlocking “T” formation.
We will be able to get a lot more Tie Downs in that space. The T Hangar
Aircraft will be displaced to the Nose dock hangars, with a parking lot behind
it. The FBO’s
will bid on ground services and the bid winner will be parking your aircraft,
but you are free to chose whomever you want for fuel services. Bill
Hopper emphasized that the relocation of aircraft for the
project will be “over-coordinated” and owners will be invited to watch the
moving of their planes. The window of opportunity to move the planes out of the
hangars will be approximately one week.
Once the pavement is gone your aircraft may be stuck there. We want to do what we can to make this have
as little effect as possible on the GA tenants. The details of the contract and
specifications with the FBO for pulling the plane in and out and response time,
etc. are still being drawn up.
This entire phase will take place between 5/11
and 7/10 but the T-Hangar area will only be disturbed for about half of that
time. It may be difficult to access property in the hangars on days when they
are paving or painting. Jim
Jackson asked about the slope between hangar 3 and hangar 2. Woody Wilson of HTA replied they would be
installing a trench drain the whole length of the T hangars on the low side,
approximately 10 or more feet from the Hangar buildings. The
asphalt ramp grades will be extended out to the trench drain so it will still
be sloped from both sides but won’t be as steep. A hangar 3 tenant expressed concerns about
losing the “flat spot” between hangar 2 and hangar 3 on which he parks when he
comes in and shuts down. It is important
to have a spot where the airplane will not move when they get out or when they
are refueling. Mr. Wilson said he would
take a look at the grading and see if something can be done about it. The guillotine will not be used in or around
the T-Hangars. Rather, the concrete will
be saw cut and pulled out. The asphalt crew will need to be able to open
the doors that hang out off the building to remove the old asphalt and repave
it. So tenants will want to secure or at
least cover any valuable such as tools that are in there. Though we will be watering the area to
prevent it, some dust will be created. Phase
four will take 60 days between July 11 and September 18. Phase 4A will take 30 days sometime during
that same period. Phase 5 will be from
September 19-November 20.
3. USAF BCA
Project: This project will require
Taxiway A to be closed between Taxiway L and M.
They will be starting in May installing the underground re-claimer
system similar to the one already installed on their apron. There is a fuel flume there from the Air
Force days which is slowly migrating toward Haven
Well. Once the footprint has been
determined we will plan a by-pass taxiway around it. The details of aircraft
size are yet to be determined. We hope for a taxiway to accommodate a Group 4
aircraft and would like to get as big an airplane as we can in there, but that
will be determined by the exact footprint of the work. The project is still in design phases.
4. Residential Sound Insulation Project:
Construction for Phase A is completed.
Phase B will involve several homes, some historic. The second phase will go out to bid soon.
B. Airfield Maintenance: Joe McPherson
reported that the Pease Maintenance Department will be crack sealing, joint
sealing, and painting again this year, some of which will be conducted at
night. Painting may include wingspan
restrictions and in some cases a 15 minute PPR. Pavement and airfield lighting
maintenance will be ongoing as well as mowing and chasing FOD.
C. Triennial Exercise: The FAA mandates this full scale exercise of
the Pease Airport Emergency Plan once every three years. It will be conducted on May 13, 2006 from
6:30-Noon and all area police, fire and EMS will participate along with 5 area
hospitals. The scene will be staged in such a way that it will not affect
flight operations. The event takes about one year to plan and we would like to
get everyone involved. Boston Maine has
donated the use of an aircraft for the mock disaster. We are presently looking
for volunteers to play accident victims.
Volunteers will have a symptom card for EMS personnel listing their
symptoms and volunteers will act their victim role as they are triaged and
possibly transported to hospitals. A hot
lunch will be provided. To volunteer please contact Andrew
Pomeroy or Colin Mackenzie
at the Pease Airport Management Office 433-6536. Because of the date mandates
by the FAA this exercise is getting earlier and earlier in the spring and the
weather can be unpredictable. We are
hoping to conduct the next Triennial Exercise in the early fall, 2 ½ years from
now so as to have more temperate weather.
D. Airport Operations: Airport
operations personnel are on duty 24/7 and can be contacted at the office phone
# 433-6536, their cell phone # 817-9411 or their pager #564-1983. For example,
if you come in at 1 AM and will have issues coming in or out of the gate, call
tower on final and they will relay your needs to the operations agent. Part of our job is to enforce airport rules
such as making sure everyone’s badge is displayed properly, but we are also
there to help out if you have any questions or concerns. If you want to go out on the airfield to see
what field conditions are during the winter or during construction, call the
agent and they will take you out there.
The Airport Operations Agents are the people most in tune with what is
happening on the airfield and are a resource for you to use any time.
E. Pease Development Authority: George Bald
will be leaving his position of Executive Director of PDA to return to DRED on
April 3. We will have an acting director
and a search will be conducted for candidates for the position.
F. New
Hampshire Air National Guard: Andrew Smith of NHANG, BCE
reported that the
Guard has four construction projects going on this year.
1. New Fire Station: The new ARFF station is 93% complete
and is estimated to cost 6.1 million dollars. The project is expected to be completed at
the end of April. The pre-final walk
through will be conducted March 16,
2006.
2. Ramp Repair: The ramp repair project began last year and is
scheduled to restart on March 27, 2006. This project is currently 87.5% complete and
will cost 4.9 million dollars. It
encompassed 41,500 square meters of concrete. It is expected to be completed by
the end of June.
3. Hangar AFFF Replacements: $4 million has been secured from the Guard
Bureau to do hangar AFFF replacements with ATF.
It will encompass Buildings 253 (Fuel Cell) and 254 (Main Work
Hangar). It also includes renovations to
253 for roofing, bathrooms, hangar floors and exit stairwells. It is currently going out to bid.
4. Fuel Spill Clean-Up: On December
31, 2004 there was a fuel spill in which approximately 8-9,000
gallons of fuel were expelled. All but approximately 3,000 gallons were
recovered. A valve in a pit let go and for whatever reason the system did not
report it. The computer system was in the process of and has since been
upgraded, but at that time all of the safety nets that should have caught this
error were down. Environmental Engineers did a site assessment
and determined that there are three options that would work with remediation of
the site. The most likely is that they
will install a granulated activated carbon shed and will drill down borings and
put in air emersion under the water table to bubble up the remaining
contamination and collect it in wells and send it to the granulated activated
carbon shed. Anything that comes up on the water table will get pumped out to
recovery wells. The cost is
approximately $80,000/year for 5-10 years for this remediation project.
G. Air Traffic Control: Ed
Fish reported that that the ATC provides the full time Air Traffic Control in
the tower and runs the GCA on the airfield and that serves as a way for them to
train Guard Air Traffic Controllers.
This year they will have their first ever Operation Readiness
Inspection. During the month of June and from mid-August to the end of
September the GCA is going to be off the air.
You may see members out by the GCA in camouflage wearing their chemical
ensembles and practicing in June for their inspection in September. Pease ATCS
was selected by the Air Force to train Air Force Air Traffic Controllers
deploying over to Iraq and Afghanistan that needed radar certifications. Any General Aviation pilots interested in
practicing the radar approaches are encouraged to do so. For two weeks in April
there will be another batch of trainees coming in. Civilians have to do radar
approaches under VFR conditions under VFR flight plans. They cannot fly them IFR. About 7 new
trainees will be coming here out of tech school in April and staying until the
end of the year, so you may hear someone who sounds a little inexperienced, but
there is always a certified controller behind them. If you have a concern, please voice it so
that the monitor can step in and make sure everyone understands.
A
question was asked regarding waiving the weight turbulence time limit. Mr. Fish responded that it is the pilot’s
discretion to ask to have the time limit waived. ATC can waiver small behind
large, but they cannot waiver anyone following heavy aircraft.
H. Airport Security: Brian
Corliss of TSA addressed the increased security recommendations for General
Aviation since 9/11. He addressed the importance of doing proper pre-flight planning
and strongly suggested joining AOPA and requesting electronic notification for TFR’s as well as checking their website daily.
Dan
Drumheller from Airport Security thanked all the General
Aviation Badgeholders who had already responded to the GA Badge audit that was
sent out to all General Aviation Badgeholders either by email or postal mail
and reminded everyone who has not yet responded to please confirm the
information and send it back as soon as possible. The US Visits Program is a US Customs and
Border Protection program which requires certain individuals entering the
country from overseas to be cleared with specific equipment which is only
available at the terminal building. If
you are coming in to clear customs, Customs will notify airport management
through TSA and we will pass the information on to ATC so they will know where
to direct the aircraft to clear customs.
Bill Hopper said they are working to
get the FBO’s bonded so aircraft can go there first
and then be transported to Customs by van.
Dan also announced that Gate P1 (the pedestrian gate to the GA area) has
been up and functional for two weeks.
The airside gate can only be opened once the landside gate is
secured. There is an emergency exit
button, but please do not use this unless it is absolutely necessary, such as
if your card no longer functions or if there is an electrical outage and you
are stuck. Access events are logged by
the card reader and we will go back and check who used the emergency exit and
the user will need to explain to our satisfaction why the emergency button was
necessary. We plan to put a glassed in
bulletin board in the sally port area to post notices that would be of interest
to GA users, such as announcements for meetings. Gate 26, the vehicle gate by the T hangars
may be staffed and left open at times during the construction process. When
this is the case, the security agent manning the gate will need to see your
badge to log your access, so please have it ready. When the gate is closed, it
can be accessed as usual with your gate tag.
There
have been a couple of occasions on which both the airside and landside hangar doors
were left open, breaching security. If
you are in the hangar and can see people entering and challenge them, it is
permitted, but please be aware of your responsibilities.
I.
Next Meeting: Bill
Hopper stated that since we are now holding these meetings
twice a year, they would be most beneficial as a pre-construction meeting and a
pre-snow meeting. It was determined that Wednesday at 6:30PM was an agreeable time. The next meeting will be held September 16, 2006 at the same time,
location to be determined.
J. Open Discussion:
Jim Jackson
commented that the snow plowing operation by the PDA around the T Hangars, the
taxiways and surrounding areas was excellent this year. Andrew Pomeroy
mentioned that the Pease Airport Maintenance Crew has been nominated for an
award for excellence in snow removal. Any airport users feeling the award is
deserved are encouraged to write a letter before the end of this month and
Andrew will forward them to the committee.
A question was asked regarding
preconstruction meetings. Bill
Hopper stated that there will be a lot of communication,
numerous meetings from all hands to individuals before the T Hangar
construction begins. Andrew
Pomeroy stated that the goal is to meet with each individual T-Hangar
owner and look at the hangar and discuss concerns. With permission to pull the aircraft out,
they will photograph the plane and the hangar to ensure it is returned in the
same condition.