To: All Members
From: Pease Development Authority, Airport Management Department
Date:
I.
Date Held:
III. Chairperson: Amber Goodspeed, PDA-Airport
IV. Members Present: Harold Shaw, TSA
Jim Jackson, T-Hangars
Beth Demaine, PDA-Airport
Tony Reagan, NHANG
Richard Peatfield, ATCS
Brian Corliss, TSA
V.
The following items were discussed or actions proposed or taken as indicated:
A. Expected FBO traffic (especially Part 139):
1.
2. Pan Am Services (PAS): PAS
will be handling corporate traffic this week along with a 757 tomorrow at
B. NHANG HHQ Operations:
Aircraft Arrival Departure
KC-135R 12-Nov @
Additionally
there will be increased activity on the Guard ramp as they will be moving aircraft this weekend.
C. CY06 Construction:
1.
2.
General
Aviation Apron Reconstruction/ Taxiway A OFA: This week the contractor will have to grind and
repave to eliminate areas of ponding created in the
initial construction. There were problems with the equipment this weeks so they
will resume on Monday Phase 6 has begun outside the fence with prep work for
the apron extension. A T-Hangar
tenant/Contractor meeting will be scheduled in order to go over issues from
this project so far. T-Hangar tenants and owners will receive an email or
posted invitation to this meeting which will also be attended by Pike, Pike’s
insurance representative, HTA, and representatives of Pease Development Authority.
The meeting will be held at 360 Corporate Drive in the evening at a date yet to
be determined. The project will be continued in the spring of 2007.
The
Taxiway A OFA project is currently completed for the
season. Some items have been added to this project including hold lines, new
markings and signage on both ends in order to meet FAA requirements, and
possibly runway and sensor scan systems. These additional items will probably
not be addressed until spring.
3. Sound Insulation Project: Construction
on the structures in Phase 2 is on schedule and should be completed by Thanksgiving.
Work is being done simultaneously on many structures. Phase 3 homes have been
identified and designed. The third phase should go out to bid in early 2007.
5. FMQ-19: The FMQ-19 weather equipment has
been installed and the glitch on the resistance on the grounding grid was resolved.
However, the ceilometer failed in final testing. Once
the entire system is functioning properly it will be signed off locally. The FMQ-19 is automatic sensing device on the
airfield and the information will be sent to the weather observer to be
validated and released. Once the project is completed the weather observers
will be moved to the ATC tower. There will be a phone line in addition to the
ATIS, but the information provided there will not be “official.”
D. Airport
Maintenance: Airfield maintenance will
include preventative maintenance on lighting and other projects in preparation
for the winter season. They will also be painting the terminal lead in lines.
E. Wildlife: Several
turkeys have been sighted on the airfield and chased off in the past week.
F. Security: The threat level remains at
A Security Directive was also issued requiring Airport Operations and Security Agents to conduct
random checks and inspections of vehicles in the secured area.
There
will also be a change in badging procedures, particularly regarding escorts. A
plan has been submitted for approval.
Additional information will be made available once the plan has been
approved. There will be communication
with signors and badged individuals regarding escorting privileges.
Please
continue to challenge and be observant and report anything suspicious to
Airport Operations. Ground Vehicle Procedures training classes will continue to
be held in the Airport Management Conference Room,
Security and Ground Vehicle Procedures
Class Schedule:
Nov 7 Security @
No
class on the Nov 14
Nov 21 GVP
@
Nov 28 Security @
G. Other:
1. The annual FAA
certification inspection will take place November 13-15th. Invitations will go out for the
2. The
3. The GCA will close 22 Nov
@
4. Jim Jackson asked if the contractors
would continue to fill on the outside of the fence. Amber did not have a definite answer, but
will ask Andrew Pomeroy to contact Mr. Jackson regarding the matter.
H. Meetings: (All meetings are open to the public unless otherwise noted.)
1.
The 2006-7 Snow
Meeting will be held on
2.
The annual FAA
Certification Inspection In-Brief will be held on
3.
The next PDA Board
of Directors Meeting will be held
4.
The next Quarterly
Security Meeting will be held Thursday,
5.
The next Noise
Compatibility Committee Meeting will be held Thursday,
6.
The next Quarterly
Wildlife Meeting will be held
Tuesday , 1/23/07 @ 1:00PM in the Airport Management Conference Room,
immediately followed by a 2007 Upland Sandpipers and Mowing Management
Meeting.
7.
The next Users
Group Meeting will be held in March 2007 (date to be determined) at the new
ARFF Station.
* Not open to the public due to security sensitive
subject matter.